Truss Installation

Location Southeast Michigan
Challenge Installation of 150’ box utilities truss over operating road critical to plant operations and 24/7 schedule.
Solution Monarch Welding's plan entailed building the truss away from the operating road, loading the truss with all conduits and piping, then moving the completed section into position and lifting. The lifting went according to our PE Stamped Lift plan, utilizing two cranes and two semis for the transport, and four man lifts to access the corner columns during the lowering into position.